How much profit did I make on this roofing job?

You’ve finished the job. Invoice is sent. Customer’s happy.

But here’s the question most roofers never actually answer: Did I make any money on that job?

Not “did I get paid,” that’s different. I mean, after all the costs, all the hours, all the extras you threw in, what was actually left?

If you can’t answer that in about 30 seconds, you’ve got a problem. Because if you don’t know which jobs made you money and which ones didn’t, you’re flying blind. And you’ll keep quoting the same way, making the same mistakes, and wondering why you’re working your arse off for bugger all at the end of the month.

Let me show you how to actually work it out.

Start With What You Quoted

Pull up the original quote you gave the customer.

What did you say the job would cost?

Write those numbers down. That’s your baseline.

Now Add Up What It Actually Cost You

This is where it gets uncomfortable. Because most roofers don’t track this properly, so they’ve got no idea what the job really cost them.

Here’s what you need to include:

Labour costs:

Take the actual days worked and multiply by your daily labour rate. If you’re paying a lad £180/day and you’re on the tools yourself, you need to cost your time too. Let’s say £200/day for you.

Materials costs:

Pull your supplier invoices. Add it all up.

Extras you didn’t charge for:

Cost those. Even if you didn’t charge for them, they cost you time and materials.

Other costs people forget:

Do The Maths

Now you’ve got two numbers:

Total you charged the customer: £4,200

Total it actually cost you:

Total cost: £2,800

Profit: £4,200 – £2,800 = £1,400

Not bad, right?

But hang on. You worked 2 days on the tools yourself. That’s £400 of your time. If you take that out, your actual profit is £1,000.

Over 3.5 days of work (including your time), that’s £285/day.

Is that what you wanted to make? Or did you think this job was going to clear you £2k+?

What This Actually Tells You

Once you’ve done this for a few jobs, patterns start to show up:

Jobs always run over by half a day? Your quotes are wrong. You’re underestimating labour.

Materials always cost more than quoted? You’re either not tracking supplier prices or you’re absorbing waste you shouldn’t be.

You’re always doing extras for free? You need boundaries. “While you’re here” requests need to be quoted separately or you’re working for nothing.

Certain types of jobs always underperform? Stop quoting them so low. Or stop doing them altogether.

Why Most Roofers Don’t Do This

Because it’s uncomfortable.

You don’t want to know that the job you thought made you £1,800 actually made you £340.

But here’s the thing: if you don’t know, you’ll keep doing it.

You’ll keep quoting the same way. Keep absorbing the same costs. Keep doing extras for free.

And you’ll keep working 50-hour weeks wondering why there’s nothing left at the end of the month.

What To Do Next

Start tracking this. Properly.

After every job, spend 10 minutes:

After 10 jobs, you’ll see exactly where the profit’s going.

Then you can fix it.

Most roofers are working twice as hard as they need to because they never look at what jobs actually cost them.

Don’t be one of them.